水泵电机气密测试排在哪一步?久巨水泵电机装配线的检测顺序
2水泵电机的气密测试排在总装之后、通水或浸水试验之前,因为机封端面与出线护套都要等总装才最终成形。顺序固定为电气测试、总装、气密、通水或浸水、空载运行。
View Full Version本条视频为水泵电机自动组装线实拍案例,从零部件上料、压装、检测到成品下料全流程Automation作业,设备运行稳定、衔接流畅,自动化程度拉满!直观展示高效、省人、高精度的Water pump motor complete line assembly programThe company's products are designed to improve quality and efficiency for mass production of electric motors.
水泵电机的气密测试排在总装之后、通水或浸水试验之前,因为机封端面与出线护套都要等总装才最终成形。顺序固定为电气测试、总装、气密、通水或浸水、空载运行。
View Full VersionA fully developed automated motor assembly line can replace a large number of workers, with production capacity and consistency far exceeding those of traditional methods. This video explains the challenges of manual assembly and the key advantages of automated production lines.
View Full VersionAxial-flow fan motors feature a disc-type structure and require extremely high assembly precision. This video provides a step-by-step breakdown of the entire process, from stator varnishing and magnet mounting to stator-rotor assembly, adhesive application and curing, and finally testing and encapsulation.
View Full VersionJiuju Automation provides automated assembly solutions for drive motors in new energy vehicles, integrating key processes such as winding, magnet insertion, magnetization, and testing to ensure high efficiency, high consistency, and full traceability throughout the entire process.
View Full Version